Proyek EPC Pembangkit Listrik Tenaga Panas Bumi

Project Cases

PT Rekayasa Industri membangun 60% dari seluruh pembangkit listrik panas bumi di Indonesia. Selalu terdapat hal spesifik dan unik dalam setiap Pekerjaan EPC – Pengembangan Panas Bumi di Indonesia.

Materi ini dikumpulkan dari beberapa dokumen proyek Pembangkit Listrik Tenaga Panas Bumi (Geothermal Powerl Plant) yang dikerjakan oleh PT Rekayasa Industri yaitu :

  1. Proposal Stage of Lumut Balai Project
  2. Project Execution of Lahendong Unit-5 & 6
  3. Project Execution of Muara Laboh Project
  4. Project Execution of Rantau Dedap Project

Skema EPC

[su_tabs active=”1″ vertical=”yes”][su_tab title=”Steamfield” disabled=”no” anchor=”” url=”” target=”blank” class=””]Full EPC

[/su_tab]
[su_tab title=”Power Plant” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  • Power Island
    • OPSI 1 : E & P by Penyedia Teknologi (sebagai Partner atau Vendor) > Performance Guarantee
    • OPSI 2 : Full EPC sebagai Kontraktor Tunggal >Performance Guarantee
[/su_tab][su_tab title=”Utility, Electrical, & Switchyard” disabled=”no” anchor=”” url=”” target=”blank” class=””]Full EPC

[/su_tab]
[su_tab title=”Transmission” disabled=”no” anchor=”” url=”” target=”blank” class=””]Full EPC

[/su_tab]
[/su_tabs]

Power Island Scope

  1. Resources (Engineering – Manpower Load)
  2. Schedule Proposal Development
  3. Competitiveness (Akurasi Price)

Schedule

Critical Path, Typical Project

Durasi Proyek

Durasi proyek ditentukan oleh:

[su_tabs active=”1″ vertical=”yes”][su_tab title=”Kapasitas Pembangkit” disabled=”no” anchor=”” url=”” target=”blank” class=””] [/su_tab]
[su_tab title=”Scope” disabled=”no” anchor=”” url=”” target=”blank” class=””]Diluar normal scope (Steamfield, Power Plant, Switchyard/Transmission):
o Infrastrucure (Jembatan, Jalan, etc.)
o Wellpad

[/su_tab]
[su_tab title=”Lokasi Proyek” disabled=”no” anchor=”” url=”” target=”blank” class=””]Remote area menambah waktu mobilisasi dan logistic, serta meningkatkan resiko sosial

[/su_tab]
[su_tab title=”Kondisi Lahan” disabled=”no” anchor=”” url=”” target=”blank” class=””]o Lahan tidak rata (perbukitan/lereng gunung), akan menambah waktu buat cut & fill, export import tanah, soil improvement, etc.
o Tipe tanah

[/su_tab]
[su_tab title=”Tipe Pemilik Proyek” disabled=”no” anchor=”” url=”” target=”blank” class=””]Penyesuaian kultur kerja, khususnya client asing

[/su_tab]
[/su_tabs]

KEY Milestone

[su_tabs active=”1″ vertical=”yes”][su_tab title=”Contract” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Site Handover (M-0) Wellpad (as required)
  2. Geothermal Energy (Steam) Availability (M-19)
  3. Backfeeding (M-21)
  4. Plant Start-Up/Initial SYNCHRONIZATION (M-22,5)
  5. COD / Completion (M-24)
[/su_tab]
[su_tab title=”Others” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Mobilisasi Civil Sub-Contractor (M-6)
  2. Cooling Tower (13 Months Concrete Type, 10 Months FRP Type)
  3. Steel Structure (M-12 at Site)
  4. Overhead Crane (M-14 at Site)
  5. Condensor (M-15 at Site)
  6. STG & Hotwell Pump (M-16 at Site)
[/su_tab]
[/su_tabs]

Construction Issues

Remote & Isolated Area

[su_tabs active=”1″ vertical=”yes”][su_tab title=”Condition” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Mountain Area, Steep
  2. High Rainfall, Foggy, Cold/Humid
  3. Conservation Area
  4. Far from Sea Port & Air Port
  5. Non-Industrial Community Area
  6. Minimum Infrastructure
[/su_tab]
[su_tab title=”Human Resources” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Limited Local Skilled Worker
  2. High Worker Turnover
  3. Medical Issues
[/su_tab]
[su_tab title=”Low Productivity” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Limited Local Resources
  2. Climatic Condition
  3. Delivery Time
  4. Permits
[/su_tab]
[su_tab title=”Minimum Infrastructure” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Access Road
  2. Public Facilities
  3. Communication Network
[/su_tab]
[su_tab title=”High Cost” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Working Method
  2. Delivery / Transportation Method
  3. Access Road Maintenance
  4. Logistic & Accommodation
  5. Mobilization / Demobilization Cost
  6. Weather Downtime
  7. Worker Compensation/Allowances
  8. Social Compensation
  9. Monopoly / Cartel
[/su_tab]
[su_tab title=”Social Aspect” disabled=”no” anchor=”” url=”” target=”blank” class=””]
  1. Limited Local Resources
  2. Access Road Blockage
  3. Land Ownership
  4. Sand/Agregat Supply
  5. Monopoly/Cartel
[/su_tab]
[/su_tabs]

Unforeseen Condition

  1. Geotechnical : Foundation design and slope stability issues
  2. Weather : Rainy season troughout the year, and strong winds
  3. Access Road : Community blockage, landslide issues, and road maintenance